The Once and Future Boyes Boulevard Bridge

It was a different experience in 1955

On February 17, 1955, the Index Tribune reported

“A $12,987 contract for rebuilding the Boyes boulevard bridge across Sonoma Creek, near the Bath House in Boyes Hot Springs, was awarded by the county supervisors last week…The contractor will use existing abutments and piers for the bridge and will use but relocate existing steel stringer and add a reinforced concrete deck and sidewalks.”

Thursday, March 3, 1955. Work was “in high gear” on the new Boyes Blvd. bridge.The caption notes that motorist will be forced to use “Verano Drive or Santa Rosa Avenue” to cross the creek. Verano Drive is now Verano Blvd. and Santa Rosa Avenue is West Agua Caliente Road.

Work went fast: On April 17th we learn,

“New Boyes Bridge May Open to Traffic This Weekend.”

“Possibility that the brand new bridge across Sonoma Creek at Boyes Boulevard, near the Bath House, will be open to traffic on Saturday was seen this week.

Painting of the new steel barriers and upper portion was completed on Tuesday with only the sand blasting and painting of the steel sections beneath the bridge remaining.

Normally, twenty-one days is allowed for the concrete to set after the deck has been poured. If this procedure were followed, the bridge would not open until next Monday. However, due to the excellent weather and the fact that the Boyes Hot Springs Bath House and facilities will be open for the season on Saturday, this weekend may possibly see the new bridge in use.

The Fred Fedenburg firm of Temple City has been the contractor for the $12,987 project, which was stared the last week of February.”

The work was fast because they did not replace the abutments, unlike the current project for which massive new concrete supports were poured. Still, the end of February to the end of April is rapid!

Fast forward to the year 2000. It was proposed to widen the bridge to three lanes, but neighbors worried about increased traffic.

That project never came to pass.

In December 2020 the County sent this notice informing us of a big step in the construction of the NEW new bridge.

We first learned of the current bridge project in July of 2019, when the Sonoma County Department of Transportation told the Index Tribune that the Boyes Blvd. bridge was “functionally obsolete.”

“The new replacement bridge will comply with current roadway, drainage and bridge standards…; it will not increase vehicular capacity but will provide shoulders for bicycles and a five-foot wide sidewalk for pedestrians” the IT reported.

Engineering work started in 2013. The funds were allocated in July of 2019.

“The entire project is expected to cost $5.13 million, almost 13 percent higher than originally estimated. Additional costs are said to stem from the temporary pedestrian bridge which will also provide a structure for water, gas and electric relocations, and the water systems improvements by the Valley of the Moon Water District (VOMWD).”

“Commencement of construction of the project has been delayed due to, among other things, a lengthy negotiation with a neighboring homeowners’ association in 2018,” said the summary report.

The “other things” causing delay now include a world-wide pandemic and a bad fire season in 2020. Currently the bridge is scheduled to open in July of this year (2021).

The Bridge, looking west, March of 2019
Looking east, 2008

The photos below span November 2019 through April, 2021.

Bonus slideshow of arty construction images! You’re welcome.